Project Status
As at February 25, 2010
- Millwork complete.
- Modular tie-ins complete.
- Ceiling Tile install complete
- Flooring install on going.
- Lighting install complete
- Fixture install complete
- Gym Equipment install complete
- Gym Flooring install complete
- Toilet Partition install complete
- Taping complete
- Final coat complete
- Wood Doors complete
- Commissioning started
- Carpet install complete
As at Janaury 25, 2010
- Millwork ongoing.
- Modular tie-ins ongoing.
- Ceiling Tile install ongoing
- Flooring install on going.
- Lighting install on going
- Fixture install on going
- Gym Equipment install ongoing
- Gym flooring install complete
- Toilet Partition install complete
- Taping complete.
- Final coat started
As at December 25, 2009
- Millwork ongoing.
- Modular tie ins ongoing.
- Ceiling Tile install started
- Flooring install on going.
- Lighting install on going
- Fixture install on going
- Gym Equipment install started
- Gym Flooring install started
- Toilet Partition install started
As at November 25, 2009
- Millwork ongoing.
- Modular install complete.
- Modular tie ins started.
- Ceiling Tile install started
- AHU2 start up complete.
- Flooring install on going.
As at October 25, 2009
- Metal Cladding complete.
- Taping complete.
- Prime and first coat painting complete.
- T-bar complete.
- Landscaping complete.
- Millwork install started.
- Flooring install started.
As at September 25, 2009
- Metal Cladding on going.
- Interior Board complete.
- Interior Stud complete.
- M&E Rough-ins complete.
- Taping ongoing.
- Prime and first coat painting ongoing.
- Firestopping complete.
- Landscaping started.
- Ceramic Tile started.
As at August 25, 2009
- Metal Cladding on going.
- Interior Board ongoing.
- Interior Stud complete.
- Interior Block complete.
- M&E Rough-ins to walls complete.
- Taping started.
- Prime and first coat painting started.
- Site concrete ongoing.
- Paving complete.
As at July 25, 2009
- Aluminum Windows Complete.
- Interior Mechanical and Electrical rough ins on going.
- Interior Block on going.
- Interior Steel Stud on going.
- Metal Cladding on going.
- Interior Board started.
- Brick Veneer complete
As at June 25, 2009
- Aluminum Windows started.
- Exterior Stud and Board Complete.
- Slab pours complete.
- Interior Mechanical and Electrical rough ins started.
- Interior Block started.
- Roofing Complete.
- Interior Steel Stud started.
- Metal Cladding Started.
As at May 25, 2009
- Exterior Masonry complete.
- Masonry Veneer started.
- Parapets and Roof Curbs complete.
- Site Services compete.
- Mechanical and Electrical under slab complete.
- Roofing complete.
- Roof Anchors complete.
- Metal Cladding vapour barrier started.
- Slab prep complete.
- Slab pours started.
- Interior stud and board started.
- Interior Masonry started.
As at April 25, 2009
- Structural Steel complete.
- Metal Deck complete.
- Exterior Stud and board started.
- Exterior Masonry started.
- Parapets and Roof Curbs started.
- Mechanical and Electrical under slab started.
- Mechanical and Electrical exterior wall rough ins started.
- Roofing started.
- Site Services Started.
As at March 25, 2009
Construction: Structural steel erection commenced on February 19th. Structural steel erection was the focus for the remainder of February as well as the majority of March, completing March 30th /09.
Design: “Issued for Construction” drawings have been completed and issued to all sites for use. Some changes are being made through RFI’s and Site Instructions.
As at: February 25, 2009
Construction: During the past month we have completed the pile caps, grade beams, mechanical and electrical undergrounds, foundation and interior backfill to the deep services. Structural steel was delivered on February 17th with erection commenced on February 19th. Structural steel erection will be the focus for the remainder of February as well as the majority of March.
Design: Issue for construction drawings and specifications have been issued with site instructions being issued to deal with any concerns. Issue for contract drawings and specification will be released shortly.
As at: January 25, 2009
Construction: During the past month the piling, excavation for the pile caps and grade beams have been completed with the formwork, rebar, and concrete.
Design: The design has advanced over the past month with the completion of many specific details and the specifications.
As at: December 25, 2008
Construction: Excavated for the building pad to sub base and piles have started. Design is now complete to IFCR drawings.
Design: Drawings have progressed to 95% complte and issued for construction review drawings have been posted.
As at: November 25, 2008
Construction: New anticipated construction start date is November 26,2008. Awaiting commercial footing and foundation permit. Top soil has been removed and hauled off site. Over the next month the piling will be complete and the grade beams will have started.
Design: Since the last report period, design has advanced and is now 85% complete. Over the next month we anticipate having the design complete to I.F.C. drawings.
|