Project Status
As at February 25, 2010
- Main floor final coat of paint is complete.
- VCT on main floor is complete.
- Gym floor is complete.
- Gym equipment is complete.
- Millwork installation is complete.
- Toilet partitions and washroom accessories are complete.
- Ceiling tile on the main floor is complete.
- Building is under Honeywell control.
- AHU 1 has been fired.
- Air and water balance has commenced.
- Elevator is complete.
As at Janaury 25, 2010
- Second floor final coat of paint was completed.
- Main floor final coat of paint has commenced.
- AHU 2 has been fired.
- VCT on main floor has commenced.
- Interior smoke baffles and handrail glazing are complete.
- Gym floor line painting and finishing are complete.
- Mechanical controls for AHU 1 are complete.
- Main floor lighting is complete.
As at December 25, 2009
- Main floor painting prime and first coat is complete.
- Installation of main floor T bar is complete.
- Installation of main floor radiant panels is complete.
- Main floor lighting fixtures are complete.
- Music room acoustic panels are complete.
- AHU 2 is ready to start.
- VCT on second floor is complete.
- VCT on main floor has commenced.
- Installation of ceramic tile is complete.
- Gym floor hardwood installation is complete.
As at November 25, 2009
- Main floor painting has commenced.
- Installation of the elevator is complete.
- Second floor millwork installation is complete.
- Second floor lighting fixtures are complete.
- Second floor ceiling tile is complete.
- Installation of main floor radiant panels has commenced.
- Boiler has been fired.
- AHU 2 is ready to start.
- VCT on second floor has commenced.
- MISA work has been completed.
As at October 25, 2009
- Main floor mechanical rough is complete.
- Second floor radiant panels are complete.
- Second floor millwork installation has commenced.
- Boiler installation is complete.
- AHU installation is complete.
- Exterior cladding is complete.
- Second floor T bar ceiling grid is complete.
- Main floor taping is complete.
- Main floor painting has commenced.
- Installation of the elevator has commenced.
- Landscaping is complete.
As at September 25, 2009
- Main and second floor mechanical rough is nearing completion.
- Second floor prime and finish painting is complete.
- Boiler installation is ongoing.
- AHU’s installation is ongoing.
- Fire proofing is nearing completion.
- Exterior cladding is nearing completion.
- Exterior doors and hardware are installed.
- Second floor drywall is complete.
- Second floor T bar ceiling grid is nearing completion.
- Main floor boarding is complete.
- Sidewalks are complete.
As at August 25, 2009
- Main floor steel studding is complete.
- Second floor drywall is complete and taping is nearing completion.
- Second floor prime painting is complete.
- Main and second floor electrical rough in is complete.
- Main and second floor mechanical rough is nearing completion.
- Boiler installation is ongoing.
- AHU’s installation is ongoing.
- Fire stopping is complete.
- Fire proofing is nearing completion.
- Asphalt paving is nearing completion.
- Rough grading is complete.
- Module grade beams are complete.
As at July 25, 2009
- Exterior drywall complete.
- Main floor steel studding nearing completion.
- Second floor drywall nearing completion.
- Prime painting commenced.
- Roofing complete.
- Air vapour barrier complete.
- Interior masonry complete.
- Exterior split faced concrete block complete.
- Glazing complete.
- Main and second floor mechanical and electrical rough in ongoing.
- Sprinkler lines complete and tested.
- Boiler installation ongoing.
- AHU’s delivered.
- Fire stopping commenced.
- Fire proofing commenced.
- Car plugs and bollards complete.
- Exterior curbing complete.
- Asphalt nearing completion.
- Rough grading nearing completion.
- Module grade beams commenced.
As at June 25, 2009
- Concrete slab on grade complete.
- Exterior drywall nearing completion.
- Second floor steel studding complete.
- Main floor steel studding commenced.
- Roofing nearing completion.
- Interior masonry nearing completion.
- Exterior split faced concrete block commenced.
- Aluminum windows complete.
- Barrier curbs complete.
- Roof parapets complete.
- Underground site electrical complete.
- Module piling complete.
- Asphalt paving complete.
As at May 25, 2009
- Tile 2 slab on grade complete.
- Exterior drywall nearing completion.
- Exterior grading complete.
- Masonry firewalls complete.
- Main floor steel studding commenced.
- Second floor steel studding nearing completion.
- Roofing commenced.
- Interior masonry ongoing.
- Barrier curbs nearing completion.
- Primary power conduit installed.
- Atco gas line installed.
- Steel stairs installed.
- Roof parapets nearing completion.
As at April 25, 2009
- Contret to second floor deck.
- Tile 2 slab on grade ongoing.
- Main floor exterior drywall nearing completion.
- Roof decking complete.
- Underground mechanical and electrical work complete.
- Exterior grading nearing completion.
- Structural steel complete.
- Masonry firewalls ongoing.
- Structural steel base plates have all been grouted.
- Exterior storm and sanitary services complete.
- Main floor drywall studding commenced.
As at March 25, 2009
Construction: Since the last report the structural steel erection has been completed, and bolting and detailing of the main floor for tiles 1 and 2 is complete. Decking of second floor to be completed this month, underground site mechanical is underway and will be complete prior to the end of this month. SOG for tile to be completed before end of month. Exterior steel stud is underway on tile 1 and boarding has started. Temporary power has been installed on site. Grading of the site to the North East of the school to match parks grading is underway.
Design: “Issued for Construction” drawings have been completed and issued to all sites for use. Some changes are being made through RFI’s and Site Instructions.
As at: February 25, 2009
Construction: Since the last report the masonry firewalls have been completed to the second floor level, structural steel erection has commenced, and the shallow mechanical piping under the floor slab in tile 2 and tile 3 have been completed.
Design: Issue for construction drawings and specifications have been issued with site instructions being issued to deal with any concerns. Issue for contract drawings and specification will be released shortly.
As at: January 25, 2009
Construction: Since the last report the elevator shaft has been completed and remaining foundation piers have been poured. The survey of the anchor bolt layout and hoarding for the masonry trade have been completed, and the masonry is underway.
Design: The design has advanced over the past month with the completion of many specific details and the specifications.
As at: December 25, 2008
Construction: Foundations and backfilling have been completed. Mechanical and electrical under slab work is complete and the elevator shaft is underway.
Design: Drawings have progressed to 95% complete and issued for construction review drawings have been posted.
As at: November 25, 2008
Construction: Earthwork commenced on site October 20, 2008 and excavation for the foundations is underway. The pad footings and piers are underway, and backfill is following. The grade beam formwork has commence and under slab mechanical and electrical will begin late November and continue into December as well as slab on grade preparation including granular material. Masonry will commence mid to late December.
Design: Since the last report period, design has advanced and is now 86% complete. Over the next month we anticipate having the design complete to I.F.C. drawings.
|