Tamarack Public

City:

Edmonton

                   

School Board:

Edmonton School District

                   

Grades:

K-9

                   

# of Students:

850

                   

Location:

 


                   

Start Date:

August 18, 2008

                   

Completion Date:

June 30, 2010

                   

Photo Gallery:

Click Here

                   
                       

Project Status

As at February 25, 2010
- Commissioning is complete.
- Air and water balance is complete.

As at January 25, 2010
- Gym floor was completed.
- Gym equipment was installed.
- AHU 1 was fired.

As at December 25, 2009
- Main floor millwork is complete. 

- Painting main floor is complete. 

- Main floor VCT is complete. 

- Main floor plumbing fixtures and radiant panels are complete. 

- Main floor T bar ceilings are complete. 

- Gym floor is nearing completion. 

- MISA work is complete. 

- The roof parapets are complete.  

As at November 25, 2009
-
Main floor millwork is nearing completion.
- Main floor lighting fixtures are complete.
- Gym floor has commenced.
- MISA work has commenced.

As at October 25, 2009
- Painting second floor is complete.
- T bar grid second floor is complete.
- Second floor lighting fixtures are complete.
- Second floor radiant panels are complete.
- Main floor drywall boarding is complete.
- Main floor taping is complete.
- Millwork installation second floor is complete.
- Installation of the boiler is complete.
- Installation of HVAC units is complete.
- Exterior cladding is complete.
- Permanent power is complete.
- VCT on second floor is complete.
- Main and second floor ceramic tile is complete.
- Landscaping is complete.

As at September 25, 2009
- Painting second floor finish coat nearing completion.
- T bar grid second floor is nearing completion.
- Second floor radiant panels are nearing completion.
- Ceramic tile second floor complete.
- Main floor drywall boarding nearing completion.
- Main floor taping nearing completion.
- Millwork installation second floor is nearing completion.
- Installation of the boiler is nearing completion.
- Installation of HVAC units is nearing completion.
- Exterior cladding is nearing completion.
- Permanent power and primary installation is nearing completion.
- VCT on second floor nearing completion.

As at August 25, 2009
- Site grading complete.
- Paving is complete.
- Sidewalks, light pole and car plug in bases complete.
- Painting second floor prime and first coat is complete.
- T bar grid second floor is nearing completion.
- Second floor radiant panels are nearing completion.
- Ceramic tile has commenced second floor.
- Main floor drywall boarding nearing completion.
- Main floor taping has started.
- Millwork installation second floor is nearing completion.
- Installation of the boiler is nearing completion.
- Installation of HVAC units is nearing completion.
- Exterior cladding is nearing completion.
- Main distribution and secondary power installation is complete.
- Permanent power and primary installation is nearing completion.
- Resilient floor has started on second floor. 
 
As at July 25, 2009
- Portable classroom installation complete.
- Site grading nearing completion.
- Paving nearing completion.
- Second floor drywall boarding and taping complete.
- Second floor painting has commenced.
- Main floor drywall boarding commenced.
- Installation of the boiler has begun.
- HVAC units have been delivered.
- Smoke seals are complete.
- Spray applied fireproofing is complete. 
 
As at June 25, 2009
- Portable retaining walls and screw piles are complete.
- Portable classroom installation started.
- Site grading has commenced.
- Curbing is complete.
- Paving completed.
- Roof is complete.
- Main & second floor electrical rough in is complete.
- Main & second floor mechanical rough is complete.
- Main and second floor drywall boarding has commenced.
- Installation of the boiler has begun.
- Masonry work is complete.
- Smoke seals have commenced.
- Spray applied fireproofing has commenced.
- Car plugs are complete.
- Window installation has commenced.

As at May 25, 2009
- Portable screw piling complete.
- Portable foundations have commenced.
- Site grading is nearing completion.
- The roof has commenced.
- Steel Stud framing main and second floor is complete.
- Main floor drywall boarding commenced.
- Main & second floor Electrical rough in is ongoing.
- Main & second floor mechanical rough is ongoing.
- Main and second floor block work is nearing completion.
- Exterior split face concrete block complete.
- Metal cladding of firewalls complete.
- Smoke seals have commenced.
- Spray applied fireproofing has commenced. 

As at April 25, 2009
• Roof parapets complete.
• Roof vapour barrier and rainwater leaders complete.
• Exterior drywall ongoing.
• Steel stud framing second floor ongoing.
• Second floor ductwork started.
• Second floor mechanical rough in nearing completion.
• Washroom block work complete.
• Main floor block work nearing completion.
• Main floor electrical rough in complete.
• Main floor interior steel studs nearing completion.
• Main floor drywall boarding commenced.
• Main floor mechanical rough in complete.
• Site grading ongoing.
• Dust enclosure formed and poured.
• Site services complete.
• Exterior split face concrete block ongoing.

As at March 25, 2009

Construction:  Since the last report structural steel and metal decking have been completed.  Masonry has been ongoing and is close to completion for the exterior walls and washroom areas. All exterior main and second floor walls are studded with the majority of board installed, interior studs are being installed in tile 1, and the second floor slab has been poured.  Exterior cladding has commenced with install of air/vapour barrier.  Mechanical and electrical rough-ins to main and second floor are on-going, and site mechanical service installation is underway.

Design:  “Issued for Construction” drawings have been completed and issued to all sites for use.  Some changes are being made through RFI’s and Site Instructions.

As at: February 25, 2009

Construction: Since the last report structural steel has been completed and metal decking is nearing completion. Masonry is ongoing and is close to completion for the exterior walls and washroom areas. Tile 1 main and second floor exterior walls are boarded and the second floor slab has been poured. Mechanical and electrical rough-ins have commenced.

Design: Issue for construction drawings and specifications have been issued with site instructions being issued to deal with any concerns. Issue for contract drawings and specification will be released shortly.

As at: January 25, 2009

Construction: Since the last report structurual steel erection has been ongoing, the metal deck on the second floor and roof tile 1 have been completed. Masonry has started, and installation of the exterior steel stud walls has commenced.

Design: The design has advanced over the past month with the completion of many specific details and the specifications.

As at: December 25, 2008

Construction: Site grading has continued and structural steel erection has commenced.

Design: Drawings have progressed to 95% complete and issued for construction review drawings have been posted.

As at: November 25, 2008

Construction: Grade beams and pile caps are complete, with shallow underground complete and has been inspected. The under slab electrical rough has been complete and the concrete slab on-grade complete. The water service installation will commence next week. Site grading is currently underway and is 50% complete. The structural steel will commence in December and finish in January.

Design: Since the last report period, design has advanced and is now 92% complete. Over the next month we anticipate having the design complete to I.F.C. drawings.