Rutherford West Valley Public
City: Edmonton                    
School Board: Edmonton School District
                   
Grades: K-9
                   
# of Students: 850                    
Location:
                   
Start Date: September 15, 2008
                   
Completion Date: June 30, 2010                    
Photo Gallery: Click Here
                   
                       
Project Status

As at February 25, 2010
- Air and water balancing has been completed.
- Work on deficiencies has continued.
- All Schedule C2 documents have been received from consultants.
- Commissioning is complete.
- A certificate of operation has been granted for the elevator.


As at January 25, 2010
- Line painting and base is complete in the gymnasium.
- Verification is complete on the security and fire alarm systems.
- VCT flooring has been completed in the modular corridors.
- The gymnasium divider curtain is now installed.
- The coiling grille for the servery is installed.

As at December 25, 2009

- Gymnasium hardwood is installed. 

- Mechanical and electrical fixtures are complete. 

- Ceiling tile installation is complete on second and main floor.   

- Millwork installation is complete. 

- VCT flooring is complete. 

- Installation of carpet tile is complete. 

- Commissioning of the HVAC system is complete. 

- Finish paint is complete.

 As at November 25, 2009
- Drywall and taping has been completed.
- VCT flooring has been completed on the second floor.
- Elevator installation is complete.
- Acoustic grid is complete on main floor.
- Installation of seed and sod is complete, with exception to seasonal deficiencies.
- Installation of porcelain tile is complete on the second floor and has started on main.
- AHU-2 and the boiler system are operational.
- Acoustic panels are installed in the gymnasium.
- Ceiling mounted backstops are installed in the gymnasium.
- Installation of hard wood flooring has started in the gymnasium.
- Cabinetry is installed on the second floor.

As at October 25, 2009
- Drywall and taping is near completion.
- Flooring has commenced in the second floor classrooms.
- Exterior cladding is complete.
- Modular classroom installation is complete and tie-in work has commenced.
- Elevator installation was started.
- Acoustic grid is complete on second floor.
- Installation of trees and shrubs is complete.
- Installation of ceramic tile has started in second floor washrooms.
- Heating system degrease and flush has been completed.

As at September 25, 2009
- Drywall has been completed in the gymnasium.
- Taping is complete on second floor.
- Main floor millwork is complete with exception to the library and the administration room.
- Installation of trees and shrubs is complete.
- Lights standards are installed.
- Prime coat and first coat of finish paint is complete to second floor.
- Modular classrooms have been delivered and installed to Tile 5.
- Acoustic grid is near completion on the second floor.
- Stiffened metal panels are complete.

As at August 25, 2009
- Drywall has been completed on the second floor.
- Drywall is continuing on the main floor.
- Taping has started and is continuing on the second floor, as well as continuing on the main floor.
- Electrical trade has continued with the installation of distribution panels and pulling of wire.  
- Installation of piping and equipment has continued in the boiler room and mechanical room.
- Installation of interior glazing has started and is continuing.
- Main floor millwork was delivered to site.
- Acoustic ceiling grid was started on main and second floor.
- Main distribution panel has been energized.
- Gas service has been turned on.
- Spreading of topsoil has started.
- All site sidewalks and stoops have been completed with the exception of the city walks.

As at July 25, 2009
- Mechanical and electrical rough-ins are complete to all walls.
- Air handling units have been delivered to site and are set in place.
- Electrical distribution equipment has been delivered to site and is currently being installed.
- Drywall installation is continuing on the main floor and has commenced on the second floor.
- Taping has been completed to mechanical and electrical rooms and has commenced on the main floor.
- Retaining walls and screw pile weld plates are complete for modular classrooms.
- Asphalt paving is complete.
- Seaming of PVC roofing is complete. 
- Primary power cables have been pulled and the transformer installed. 

As at June 25, 2009
- Mechanical and electrical rough-ins are complete on main floor and near completion on the second floor.
- Boiler room equipment has been delivered to site.
- Fire proofing and fire stopping has continued.
- Drywall board to main floor walls has commenced.
- The PVC roofing membrane has been installed.
- Screw piles have been installed.
- Site grading is complete.
- Split face block is complete.
- Aluminum window frames are complete.
- Metal cladding has continued to exterior walls.
- Conduits for primary power are installed.
- Curbs are substantially complete.
- Asphalt paving is complete to the playing pad.

As at May 25, 2009
- Vapour barrier is complete behind split face block and continuing to areas that will receive metal siding.
- Split face block has commenced.
- Parapets have been completed.
- Metal Siding has been completed to fire walls.
- Plumbing, electrical and HVAC rough-ins have continued to both main and second floor.
- Sprinkler mains are complete on main and second floor.
- Roofing has continued.
- Fire stopping has started.
- Site grading has started again.
- Steel stud on main floor and second floor are close to completion.
- Aluminum window frames have started.
- Interior masonry is complete. 

As at April 25, 2009
- Exterior steel stud and board complete
- Split face block has been delivered to site.
- Site storm, water, and sanitary lines have been installed.
- Parapets have continued and are near completion.
- Masonry firewalls have been completed.
- Plumbing, electrical, HVAC and sprinkler rough-ins have continued.
- Roofing has started.
- Fire proofing has started.
- Vapour barrier in areas with split face block have started.
- Interior steel stud on the main floor is near completion.
- Blocking for millwork, white/tackboards, etc. is ongoing.

As at March 25, 2009

Construction:  Since the last reporting period concrete topping has been installed to the second floor, which completes the slabs in the building.  Exterior steel stud has been completed to the main floor, boarding is underway on main floor.  Masonry has commenced for interior walls.  Mechanical and electrical rough-ins to ceiling space have commenced.

Design:  “Issued for Construction” drawings have been completed and issued to all sites for use.  Some changes are being made through RFI’s and Site Instructions. 

As at: February 25, 2009

Construction: Since the last reporting period erection of structural steel has been completed. Bolting and detailing of structural steel is continuing and will be completed in early March. Installation of metal decking to the second floor level is complete. Installation of roof deck will be completed shortly after bolting and detailing of structural steel is complete. Mechanical and electrical rough-ins to the second floor deck have commenced in preparation for second floor concrete slabs. Main floor exterior steel stud and drywall have commenced.

Design: Issue for construction drawings and specifications have been issued with site instructions being issued to deal with any concerns. Issue for contract drawings and specification will be released shortly.

As at: January 25, 2009

Construction: Since the last reporting period, the masonry work to the fire walls has been completed to the second floor level on both ends of the building, erection of structural steel has commneced and grading to the modular area at the south end has been completed.

Design: The design has advanced over the past month with the completion of many specific details and the specifications.

As at: December 25, 2008

Construction: Installation of grade beam rigid insulation has been completed along with detailed backfill and compaction. The building's main floor slab on grade has been successfully completed.

Design: Drawings have progressed to 95% complete and issued for construction review drawings have been posted.

As at: November 25, 2008

Construction: Since the last reporting period grade beams and pile caps have been completed. Installation of insulation to the grade beams is approximately half complete, while backfill is following behind. The elevator shaft will be complete near the end of November. Under slab mechanical and electrical rough-ins are now well under way, as well as preparation for the interior slab on grade. Weather permitting, all interior slab on grade should be complete before the Christmas break. Masonry is scheduled to begin the second week of December on the end walls that interface with the portables.

Design: Since the last report period, design has advanced and is now 86% complete. Over the next month we anticipate having the design complete to I.F.C. drawings.