Project Status
As at February 25, 2010
- HVAC install completed.
- Final coat of paint is on-going.
- Interior HM doors and hardware installation on-going.
- Millwork Installation on-going.
- Acoustical Panel Installation is complete in the gymnasium.
- Gymnasium Equipment installation is complete.
- M&E Finishes are on-going.
- Acoustical Ceiling tiles to be installed.
- Controls are on-going.
- Carpet is installed.
- Millwork installation completed.
- Interior glazing pressure caps installed.
- Gym Flooring installation started.
As at January 25, 2010
- Mechanical Equipment
- AHU & boilers installation is completed.
- HVAC install completed.
- Final coat of paint is on-going.
- Interior HM doors and hardware installation on-going.
- Millwork Installation on-going.
- Acoustical Panel Installation is complete in the gymnasium.
- Gymnasium Equipment installation is complete.
- M&E Finishes are on-going.
- Acoustical Ceiling tiles to be installed.
- Controls are on-going.
- Carpet is installed.
As at December 25, 2009
- Mechanical Equipment - AHU & boilers installation is ongoing.
- HVAC install on-going
- Data/Communication rough-in is complete.
- Interior Drywall boarding and Music Rooms complete.
- Painting is on-going.
- VCT & Ceramic flooring is complete.
- Interior HM doors and hardware installation on-going.
- Millwork Installation started.
- Lockers installed.
- Transformer Installed.
- Acoustical Panel Installation Started.
- Acoustical Ceiling tile Installation Started.
- M&E Finishes have started.
As at Noveberm 25, 2009
- Canopy soffits & cladding completed.
- Mechanical Equipment
- AHU & boilers installation is ongoing.
- HVAC install on-going
- Data/Communication rough-in is on going.
- Interior Drywall boarding and taping Music Rooms.
- Painting is on-going.
- VCT & Ceramic flooring is on-going.
- Interior HM doors and hardware installation on-going.
- Exterior masonry is complete.
- Roof counter and cap flashing installed.
- Exterior glazing pressure caps complete.
As at October 25, 2009
- Interior M&E rough-ins nearing completion.
- Exterior glazing is completed.
- Canopy cladding is completed.
- Mechanical Equipment - AHU & boilers installation is ongoing.
- HVAC install on-going.
- Data/Communication rough-in has started.
- Interior Drywall boarding and taping are complete.
- Painting is on-going.
- Landscaping completed.
- Flooring has started.
- Hollow metal door and hardware installation has begun.
- Exterior masonry is complete.
As at September 25, 2009
- Interior M&E rough-ins almost complete.
- Exterior glazing is completed.
- Metal cladding installation completed.
- Mechanical Equipment.
- AHU & boilers installation is ongoing.
- Interior Drywall boarding and taping are complete.
- Painting has started.
- Landscaping nearing completion.
As at August 25, 2009
- Exterior split face block is complete.
- Interior M&E rough-ins 85% complete.
- Hard play surface is complete.
- Exterior glazing is complete.
- Metal cladding install 90% complete.
- Mechanical Equipment - AHU & boilers installation is ongoing.
- Interior Drywall 90% boarded and taping has started.
- Site Grading complete.
- Landscaping began.
- Site sidewalks are complete.
As at July 25, 2009
- Exterior split face block is 95% complete.
- Interior masonry block walls are 100% complete.
- Interior steel stud is 100% complete.
- Interior M&E rough-ins is on going.
- Site deep curbs and asphalt surfaces are complete.
- Screw pile for modular’s where completed.
- Exterior glazing is 90% complete.
- Metal cladding install has been started.
- Joist reinforcing was completed.
- Mechanical room slab was poured.
- Mechanical Equipment - AHU & boilers delivered and installation has started.
- Interior Drywall has started.
- Site Grading complete
As at June 25, 2009
- Roofing has been completed.
- Exterior split face block is 80% complete.
- Interior masonry block walls are 75% complete.
- Interior steel stud is 45% complete.
- Interior M&E rough-ins is on going.
- Site deep curbs and asphalt surfaces are complete.
- Screw pile for modular’s are complete.
- Exterior glazing is 65% complete.
- Metal cladding install has been started.
- Joist reinforcing will be completed.
- Mechanical room slab will be poured.
As at May 25, 2009
- Site Services has been completed.
- Metal deck has been completed.
- Exterior masonry block completed.
- Exterior steel is completed.
- Parapets are completed.
- Exterior masonry walls are completed.
- Exterior sheathing has been completed.
- SOG Tiles 1, 2 and 3 completed.
- Roof anchors installed.
As at April 25, 2009
- Structural steel erection is completed.
- Underground mechanical and electrical rough-ins has been installed.
- Interior building pad was backfilled to underside SOG.
- Utilities, sanitary, water & sewer installation was started.
- Prefab parapets (Steel Stud & Sheathing)
As at March 25, 2009
Construction: Since the last reporting period the piling, detailed excavation for grade beams and piles caps have been completed and the sub-grade prep is proceeding as scheduled. Grade beams have been formed and poured and pile caps are complete. Mechanical and electrical underground rough-ins have been started. Structural Steel erection has begun.
Design: “Issued for Construction” drawings have been completed and issued to all sites for use. Some changes are being made through RFI’s and Site Instructions.
As at: February 25, 2009
Construction: Since the last reporting period the piling, detailed excavation for grade beams and piles caps have been completed and the sub-grade prep is proceeding as scheduled. Grade beams have been formed and poured and pile caps are complete. Mechanical underground rough-ins have been started.
Design: Issue for construction drawings and specifications have been issued with site instructions being issued to deal with any concerns. Issue for contract drawings and specification will be released shortly.As at: January 25, 2009
Construction: Since the last reporting period, the piling, detailed excavation for grade beams and pile caps have been completed the sub-grade prep is proceeding as scheduled. Grade beams have been formed and poured and pile caps are ongoing.
Design: The design has advanced over the past month with the completion of many specific details and the specifications.
As at: December 25, 2008
Construction: Earthwork for the building pad has been completed, grading for parking lot and modular locations is complete to subgrade elevations and piling has commenced.
Design: Drawings have progressed to 95% complete and issued for construction review drawings have been posted.
As at: November, 25, 2008
Construction: Since the last reporting period we have continued to setup the site and the phones have been connected, while the consultants have continued with design. Over the next month we expect to complete grading to the building pad and commence piling. The piling is anticipated to be 90% complete by the end of December.
Design: Since the last report period, design has advanced and is now 83% complete. Over the next month we anticipate having the design complete to I.F.C. drawings.
|