Project Update
As at Janaury 25, 2010
- M&E rough-ins 95% Complete.
- Mechanical Equipment – AHU & boilers installation is 95% complete.
- HVAC installation on-going.
- Boarding and Taping complete.
- Electrical Room is 98% complete.
- Prime and 1st coat of paint is on-going.
- T-Bar ceiling grid on-going.
- Building Systems running.
- Acoustical Panels in Gym are complete.
- Floor Patching complete.
- Flooring Installation has begun.
- Gym Flooring Installation started.
As at December 25, 2009
- M&E rough-ins on-going.
- Mechanical Equipment – AHU & boilers installation on going.
- HVAC installation on-going.
- Boarding and Taping 90% complete.
- Repair of sagging mechanical lines under SOG has been
completed.
- Electrical Room is on-going.
- Exterior doors and hardware complete.
- Completed the glazing pressure capping.
- Prime and 1st coat of paint.
- Drywall including Music Room bulkheads completed.
- T-Bar ceiling grid on-going.
- Building Systems running.
As at November 25, 2009
- M&E rough-ins on-going.
- Mechanical Equipment
- AHU & boilers installation on going.
- HVAC installation on-going.
- Metal Cladding including soffits and cap flashings complete.
- Boarding and Taping continuing.
- Removal and Repair of sagging mechanical lines under SOG has been completed.
- Electrical Room is on-going.
- Exterior doors and hardware complete.
- Completed the glazing pressure capping
As at October 25, 2009
-Interior masonry walls complete.
-Interior steel stud have been completed.
-M&E rough-ins on-going.
-Mechanical Equipment
–AHU & boilers installation on going.
-HVAC installation on-going.
-Metal Cladding is complete.
-Site Sidewalks are complete.
-Slab jacking was performed and completed.
-Landscaping completed.
-Soils Densification under SOG has started.
-Removal and Repair of sagging mechanical lines under SOG has been started.
-Interior drywall is ongoing.
-Electrical Room is on-going.
-Install exterior doors and Hardware.
As at September 25, 2009
- Interior masonry walls half complete.
- Interior steel stud third complete.
- M&E rough-ins on-going.
- Mechanical Equipment
- AHU & boilers installation on going.
- Metal Cladding is complete.
- Site Sidewalks are complete.
- Slab jacking was performed and completed.
- Landscaping is nearing completion.
As at August 25, 2009
- Exterior masonry complete.
- Interior masonry walls 30% complete.
- Interior steel stud 20% complete.
- Exterior window installation complete.
- M&E rough-ins to exterior walls complete.
- Site curbs and car plugs have been completed.
- Mechanical Equipment – AHU & boilers installation on going.
- Metal Cladding is on going.
- Asphalt complete.
- Site Sidewalks approximately 65% complete.
As at July 25, 2009
- Exterior steel stud and drywall completed.
- Exterior masonry 95% complete.
- Interior masonry walls 30% complete.
- Interior steel stud 20% complete.
- Exterior window installation 85% complete.
- M&E rough-ins to exterior walls complete.
- Roofing 100% complete.
- Site curbs and car plugs have been completed.
- Mechanical Equipment – AHU & boilers delivered and installation has started.
- Metal Cladding has started.
- Screw piles for the modular’s are complete.
As at June 25, 2009
- SOG and mechanical room slab complete.
- Exterior steel stud and drywall 90% completed.
- Exterior Masonry 10% complete.
- Interior masonry walls 20% complete.
- Exterior window installation 40% complete.
- M&E rough-ins to exterior walls complete.
- Roofing 50% complete.
- Roof anchors and joist reinforcing complete.
As at May 25, 2009
- Structural Steel Erection has been completed.
- Metal deck is installed.
- Mechanical & electrical shallow underground rough-ins are completed.
- Exterior masonry block is completed.
- Site Services have been installed.
- Exterior Steel stud work has started.
- Parapets are started.
- Backfill interior building foot print and prep for SOG
As at April 25, 2009
- Underground mechanical & electrical rough-ins completed.
- Grade beam and pile caps have been formed and poured.
- Structural Steel Erection has begun.
As at March 25, 2009
Construction: Since the last report, the installation of driven piles have been completed. Grade beam and pile caps have also been formed and poured. Mechanical and electrical underground rough- ins have begun.
Design: “Issued for Construction” drawings have been completed and issued to all sites for use. Some changes are being made through RFI’s and Site Instructions.
As at: February 25, 2009
Construction: Since the last report, the installation of driven piles began. Grade beam and other foundation work are now underway with excavation and forming.
Design: Issue for construction drawings and specifications have been issued with site instructions being issued to deal with any concerns. Issue for contract drawings and specification will be released shortly.
As at: January 25, 2009
Construction: Since the last report the survey for the foundations has been completed.
Design: The design has advanced over the past month with the completion of many specific details and the specifications.
As at: December 25, 2008
Construction: Commenced earthwork on site.
Design: Drawings have progressed to 95% complete and issued for construction review drawings have been posted.
As at: November 25, 2008
Construction: Documents have not been received to date permitting submission for the foundation permit. We anticipate receipt of these documents by November 21. This should allow the foundation permit to be issued by the end of November which will enable us to proceed with clearing the site in early December and completing the piles to 90% by the end of December.
Design: Since the last report period, design has advanced and is now 85% complete. Over the next month we anticipate having the design complete to I.F.C. drawings.
|