Hollick-Kenyon Public

City:

Edmonton
                   

School Board:

Edmonton School District
                   
Grades: K-9
                   
# of Students:
850
                   
Location:

                   
Start Date:
September 10, 2008
                   
Completion Date:
June 30, 2010
                   
Photo Gallery:
Click Here                    
                       

Project Status

As at February 25, 2010
- Bird-Graham and consultant deficiencies completed to 2nd floor
- Bird-Graham and consultant deficiencies completed to main floor
- AHU1 to be started up
- Mechanical and electrical commissioning to commence.

As at January 25, 2010
- Carpet and linoleum to be installed on 2nd floor;
- VCT, carpet and linoleum to be installed on 1st floor;
- Install rubber base to both floors;
- Finish paint on 2nd and 1st floor;
- Finish elevator inspection and commissioning;
- Complete mechanical and electrical fixtures install;
- Install washroom partitions and toilet accessories;
- Install ceiling tiles to 1st floor;
- Complete millwork deficiencies to 2nd and 1st floors;
- Complete Bird-Graham deficiencies to 2nd floor;
- Complete consultant deficiencies to 2nd floor;
- Commence mechanical and electrical commissioning.


As at December 25, 2009
-
Chain link fencing completed; 

- Millwork to 1st floor commenced; 

- Completed acoustical wall panels in music room; 

- Completed VCT flooring in  main corridors on both floors; 

- Completed rework on 2nd floor ceramic tile  

- Finish paint on 2nd floor commenced; 

- Completed installing gym equipment (less curtain and game posts) 

- Completed installing lockers (less modular’s); 

- Completed wood doors on the first floor; 

- Completed gym floor installation (finishing continuing); 

- Installed ceiling tiles to 2nd floor; & 

- Completed MISA work (less seasonal deficiencies).

As at November 25, 2009
- started MISA site works
- 2nd floor casework ongoing 
- wood doors completed on 2nd floor
- glazing installed at 2nd floor interior railings
- acoustical wall panels completed in gymnasium
- 1st floor ceramic tile completed
- prime + 1 coat on 1st floor completed
- done with M&E rough in
- start up AHU & boiler
- Telus installed temp service lines
- landscaping completed
- Finished drywall

As at October 25, 2009
- Landscaper to finish spreading the top soil
- start planting trees and shrubs
- finish the sidewalk and retaining wall next to Modulus
- hook up gas & permanent power to building
- installed divider curtain support framing
- complete fire spray deficiencies
- work on the exterior metal cladding
- start installing interior and exterior doors
- installing pressure caps at windows
- done with boarding in gym; continue with sheetrock tape, mud and sand on1st   
- done with T-bar ceiling on 2nd floor
- done with ceramic floor tiles on 2nd
- painting less finish coat done on 2nd floor
- start installing elevator   
- working on M&E rough in on 1st
- boiler room rough in about 60%, AHU about 95%, control about 25%
- radiant panels installed on 2nd but piping not connected yet

As at September 25, 2009
- completed sidewalk & asphalt paving
- completed portable retaining wall
- completed firespray
- work on vapor barrier / Z clips and installing metal siding
- installed glazing at windows
- rock, tape, mud and sand 1st floor wall nd
- work on hard ceiling & T bar ceiling on 2floor
- painting on 2nd floor nd
- work on mock up room on 2
- working on M & E rough in on 1st floor
- start M & E trim on 2nd floor
- work on sprinkler rough in with drops
- Permanent power update: transformer & distribution equipment floor installed; file application with Epcor upon passing of inspection

As at August 25, 2009
- work on asphalt paving
- complete installing exterior windows 
- work on 2nd floor drywall: rock, tape, mud & sand
- start 1st floor drywall boarding
- continue painting on 2nd floor & start painting on 1st
- done with M & E rough in on 2nd floor and continue on 1st floor

As at July 25, 2009
- complete FRP exterior curbs, modular grade beams and asphalt paving; continue working on sidewalks
- complete the screw piles
- complete masonry works inside and out
- be done with stair handrails
- continue with 2nd floor firespray
- complete exterior vapor barrier and z bars; took field dimension for the metal panels
- received interior doors & hardware
- install exterior doors and hardware 
- complete window frames and glazing
- complete all wall framing and blocking
- drywall rock, tape and sand done on 2nd and continues on 1st floor 
- started painting on 2nd floor
- continue with M & E rough in
- sprinkler rough in continues on 1st floor

As at June 25, 2009
- Exterior site works: Pouring curbs and walks; Completed light standards; Ready for curb & sidewalk at rear of school
- Poured concrete fill at steel stairs
- Masonry: Exterior masonry completed at the rear side of school; Gym masonry done; Start working on the masonry at the front and locker rooms; Fire caulked masonry fire wall
- Installing stair handrails
- Vapor barrier in place; Start installing exterior insulation 
- Done with PVC Roofing 
- Window frames installed on 2nd floor; Glazing completed on 1st floor
- Metal Studs & drywall: Wall framing completed on both floor; Mechanical rooms taped and ready for paint
- M & E rough ins completed on 2nd floor and on going on 1st floor

As at May 25, 2009
- Exterior steel stud and board complete
- Roofing tile 1 & 2 complete
- Mechanical and electrical rough ins for slab on grade complete
- Slab on grade complete
- Interior steel stud 2nd floor complete
- Block washrooms 2nd floor complete 

As at April 25, 2009
- deep site services completed
- sanitary, storm and water completed
- second floor slab on deck completed
- exterior steel stud and board is completed on the first floor and 2nd floor is 50% complete
- mechanical, electrical and H-vac rough ins to the roof are complete
- roof is water tight with exterior board and vapor barrier membrane is ongoing

As at March 25, 2009

Construction:  Since the last reporting period, we have completed structural steel and decking at the 2nd floor and roof level. Mechanical and electrical rough ins for the roof, 2nd floor and exterior walls are ongoing and are keeping up with our progress.

Design:  “Issued for Construction” drawings have been completed and issued to all sites for use.  Some changes are being made through RFI’s and Site Instructions.  These changes are being incorporated in to the “Issued for Contract” drawings that will be issued to Alberta Infrastructure shortly.

As at: February 25, 2009

Construction: Since last reporting period we have surveyed all the grid made good progress on the structural steel.

Design: Issue for construction drawings and specifications have been issued with site instructions being issued to deal with any concerns. Issue for contract drawings and specification will be released shortly.

As at: January 25, 2009

Construction: Sediment and erosion control measures are ongoing and changing to meet the requirements. Since the last report we have started the masonry fire walls at the portables to just above second floor level. 

Design: The design has advanced over the past month with the completion of many specific details and the specifications.

As at: December 25, 2008

Construction: Sediment and erosion control measures are ongoing and changing to meet the ESC requirements. Underground mechanical has been completed. The parking lot has been cut to sub grade. Backfilling complete. Deep mechanical rough in is complete within building footprint.

Design: Drawings have progressed to 95% complete and issued for construction review drawings have been posted.

As at: November 25, 2008

Construction: Sediment and ersion control ongoing and changing to meet requirements. Final grade is still undergoing changes so gravel will not be placed in parking lot until this design is complete. Piing is 100% complete, frade beams 100%, interior pile caps 100%. Perimeter insulation is being installed and backfilling is underway, also deep mechanical rough in has started. over the next month we anticipate completing all underground services and backfilling so we ill be ready to pour slabs.

Design: Since the last report period, design has advanced and is now 92% complete. Over the next month we anticipate having the design complete to I.F.C. drawings.