Carlton Public

City:
Edmonton
                   
School Board:
Edmonton School District
                   
Grades:
K-9
                   
# of Students:
850
                   
Location:
                     
Start Date:
September 10, 2008
                   
Completion Date:
June 30, 2010
                   
Photo Gallery:
Click Here
                   
                       

Project Update

As at February 25, 2010
- 2nd coat paint to main floor complete
- Resilient flooring 100% complete to main floor
- Ceiling tile 100% complete to main floor
- Mechanical controls 100% complete
- Bird-Graham and consultant deficiencies complete to 2nd floor
- Bird-Graham and consultant deficiencies to commence to mainfloor.

As at January 25, 2010
- Gymnasium flooring to complete installation and finishing;
- Finish coat paint to 2nd and 1st floors to commence;
- VCT to be completed to 2nd and 1st floors;
- Carpet tile and linoleum to commence on 2nd floor;
- Rubber base to commence to 2nd floor;
- Mechanical and electrical core building installation of systems to be completed;
- Mechanical and electrical fixtures to be installed to 2nd floor and to commence on 1st floor;
- Millwork deficiencies complete to both floors;
- Finish coat paint to commence to 1st floor;
- Above ceiling inspections to 1st floor by consultants;
- Complete ceiling tile installation to 1st floor; &
- Commence carpet tile and linoleum to 1st floor.

As at December 25, 2009

-
Completed the 450 mm storm line rework;  

- MISA off-site works commenced; 

- Completed landscaping (less seasonal deficiencies); 

- Architect inspected building exterior & site work;  

- Architect/Consultants inspected 2nd floor above ceiling work; 

- Completed millwork on 2nd floor; 

- Completed the cladding at canopy soffit; 

- Commence fire stopping deficiencies; 

- Completed wood door installation; 

- Commenced with hardware installation on both floors; 

- Commenced with interior sills and window deficiencies; 

- Completed acoustical panels in gymnasium;  

- Complete with T-bar ceiling on 1st floor; 

- Complete with 1st floor ceramic tile installation; 

- Commence with rework on 2nd floor ceramic tile  

- Complete VCT & sheet flooring except the corridors to 2nd floor; 

- Complete with prime + 1 coat on 1st floor; 

- Completed locker installation; 

- Complete installing gym equipment (less divider curtain and game posts/nets); 

- Completed installing elevator; 

- Completed M & E rough in (less controls); 

- Started up AHU2 and boilers; & 

- Telus installed 4 temp service lines.  

As at November 25, 2009
- landscaper planting trees
- importing and spreading 6” top soil, completed 90% of sodding, completed all mulched areas
- poured garbage enclosure pad
- completed masonry walls at garbage enclosure
- completed patch sleeve openings at fire rated wall on 2nd & 1st floors
- finish installing exterior metal cladding
- work on the casework on 2nd floor
- installing doors and hardware
- work on 1st floor drywall, tape, mud, and sand
- work on 1st floor T-bar ceiling
- complete 1st floor ceramic tile floor
- work on VCT 2nd floor   
- worked on priming plus 1 finish coat on 1st floor
- start installing elevator
- M & E rough in: Done with Boiler room, AHU and controls floor & started, radiant panels installed and connected on 2nd floor
- start degreasing and flushing out the heating lines
- Telus installed cabling to the School
- completed exterior site sidewalks
- completed asphalt paving in parking lot

As at October 25, 2009
- hook up gas service, water service and permanent power to building
- start the exterior garbage enclosure pad
- install divider curtain support framing
- installing casework on 2nd floor
- work on fire spray deficiencies
- exterior metal cladding ongoing
- interior glazing ongoing
- finish boarding the Gym wall
- tape, mud and sand sheetrock on 1st floor complete
- finish installing ceramic floor tiles on 2nd floor and start installing on 1st   
- done with 2nd floor T-bars and start working on 1st
- painting less finish coat done on 2nd and start painting the 1st floor wall
- M & E rough in done on main floor except boiler room (about 60%), AHU (about 75%), controls (about 50%)
- finish installing radiant panels on 2nd floor but they are not hooked up yet

As at September 25, 2009
- finish pouring grade beams at modular
- work on asphalt paving & work on sidewalk
- installing handrails
- work on firestopping
- complete Z-bar; insulation / siding on West at the portable classrooms & South of Tile 2
- continue with metal cladding installation on other areas
- roofing 100% done except cap flashing
- work on the exterior window sill flashing, trim @ CMU wall
- glaze interior windows
- done with 2nd floor tape, mud and sand on walls
- work on 2nd floor hard ceiling
- work on 1st floor wall boarding, continue with tape, mud and sand
- work on 2nd floor T-bar ceiling
- continue painting on 2nd floor
- done with M & E rough in 2nd floor and work on 1st floor
- work on sprinkler rough in 1st floor
-
permanent power update: main switchgear installed; working on transformer

As at August 25, 2009
- complete rough grading & sub-base for sidewalk & paving
- work on sidewalk & asphalt paving 
- work on 2nd floor firespray
- install exterior windows & aluminum doors
- work on 2nd floor wall tape & sand; continue rock, tape & sand on 1st floor
- start T bar on 2nd floor
- continue painting on 2nd floor
- continue M & E rough in on 1st floor

As at July 25, 2009
- complete FRP exterior curbs
- complete the screw piles
- complete masonry works inside & out
- done with 2nd floor firestopping
- done with firespray at stairs and continue on at other areas 
- complete exterior air / vapor barrier
- done with Z bars and took measurement for metal siding 
- start installing doors and hardware
- complete exterior windows & glazing
- complete all wall framing and blocking 
- drywall tape and sand continues on 2nd; rock on 1st 
- start 1st coat painting on 2nd floor
- start reinforcing the basketball hoops in gym
- complete M & E wall rough in on 2nd and continue on 1st floor
- transformer pedestals inspected; installing main switchgear; Per Electrical Sub’s request, Epcor is scheduled to install high voltage cables by end of July, which is followed by the transformer

As at June 25, 2009
- Exterior site works: Parking lot cut to subgrade; Subgrade cut at south of building for play surface and landscape areas; Light pole bases completed; Site services on hold because of the existing 450 mm storm line; Atco tied in the gas hook up to building
- FRP exterior light pole bases, car receptacles, flagpole and bollards
- All stair pans poured
- Complete installing blocks in change rooms west of gym
- Firestopping completed on 1st floor, and on going on 2nd floor
- Air / vapor barrier installed 
- Roofing completed except for front entrance canopy
- Doors & windows: Exterior windows & glazing installed on north wall of tile 2; All of interior door and window frames installed on 2nd floor
- Metal studs & drywall: Done with track layout on 1st floor tile 1 and continue with wall framing; Done framing front canopy area; Boiler room & mechanical room rocked; Rocked top of corridor and around HM frames on first and moving onto 2nd floor; Start sheetrock on 2nd floor
- M & E rough in continues on both floors
- Done with exterior electrical rough in
- Continue to work on electrical distribution upon the anticipated arrival of the main switchboard  

As at May 25, 2009
- Exterior site services, electrical, storm, sanitary and gas lines are complete
- All exterior split face block is completed
- Interior block work at the second floor is completed
- Interior steel stud at the second floor is completed
- Slab on grade is completed
- All rough ins for slab on grade are complete 
- Roofing tile 1 & 2 complete

As at April 24, 2009
- Plumbing , electrical, and H-vac rough ins complete
- Curbs for equipment at the roof level complete
- Roofing system which is water tight
- Ground thaw complete
- Start all shallow under slab rough ins
- All exterior steel stud and board except the curtain wall area is complete

As at March 25, 2009

Construction:
  Since the last reporting period, the exterior steel stud and drywall has been completed on the north face of tile 1 and 2  for both the first and second floors. We have completed the roof  fall arrest anchors and the parapets. Plumbing and mechanical rough ins on the roof level have been completed to allow us to start the roof exterior board and air vapor barrier for tile one. We have also completed the masonry gym walls.

Design: “Issued for Construction” drawings have been completed and issued to all sites for use.  Some changes are being made through RFI’s and Site Instructions.  

As at: February 25, 2009

Construction: Since the last reporting period, structural steel erection is complete and both fire rated masonry walls at the portables are complete. Second floor decking is complete with roof decking on going.

Design: Issue for construction drawings and specifications have been issued with site instructions being issued to deal with any concerns. Issue for contract drawings and specification will be released shortly.

As at: January 25, 2009

Construction: Sediment and erosion control measures are ongoing and changing to meet the requirements. Since the last report we have started structural steel and anticipate it being completed over the next month. 

Design: The design has advanced over the past month with the completion of many specific details and the specifications.

As at: December 25, 2008

Construction: Sediment and erosion control measures are ongoing and changing to meet the erosion and sediment control requirements. Piling is 100% complete. Grade beams and pile caps 100% complete. Perimeter grade beam insulation and backfilling complete. Deep underground services are completed as well.

Design: Drawings have progressed to 95% complete and issued for construction review drawings have posted.

As at: November 25, 2008

Construction: Sediment and erosion control measures are ongoing and changing to meet the erosion and sediment control requirements. Piling 100% complete, Grade beams and pile caps 100% complete, perimeter Grade beam insulation being installed and backfilling taking place. Deep underground services have started as well, in building footprint. Over the next month we ill anticipate starting structural steel and completion of the steel to 25%.

Design: Since the last report period, design has advanced and is now 91 % complete. Over the next month we anticipate having the design complete to I.F.C. drawings

 