Project Status
As at February 25, 2010
- Gym floor installation complete.
- 2nd floor deficiency list created.
- Wood Doors 1st floor complete.
-1st floor mechanical finishing complete.
-1st floor electrical finishing complete.
-1st floor ceiling tile complete
-1st floor final coat paint complete
As at Janaury 25, 2010
- 1st floor T-bar complete.
- 1st floor HM doors complete.
- 1st floor porcelain tile complete
- 2nd floor glass railing complete.
- 1st floor millwork complete
- 1st floor sheet vinyl compete
- Gym floor installation started.
- 2nd floor deficiency list created.
- 2nd floor finish coat completed.
As at December 25, 2009
- HM Doors 2 floor complete.
- 2nd floor mechanical finishing complete.
- 2nd floor electrical finishing complete.
- 2nd floor ceiling tile complete
- 1st floor prime +1 complete.
- 1st floor T-bar started.
- 1st floor HM doors started.
- 2nd floor porcelain tile complete
- 2nd floor glass railing started.
- 2nd floor millwork complete
- 1st floor VCT started
- 1st floor porcelain tile started
- Permanent Power installed
As at November 25, 2009
- Fencing complete
- 2nd floor electrical finishing started.
- 2nd floor mechanical finishing started.
- Driveway entrances complete.
- 1st floor taping and sanding complete.
- Landscaping complete.
- 2nd floor VCT complete
- 2nd floor porcelain tile complete
- 2nd floor carpet complete.
- 2nd floor glass railing started.
- 2nd floor HMD complete
- 2nd floor millwork complete
- 2nd floor lockers complete.
- Gym Acoustic Panels complete
As at October 25, 2009
- Cladding complete.
- 2nd floor T-bar complete.
- 2nd floor millwork complete
- 2nd floor electrical finishing started.
- 2nd floor mechanical finishing started.
- 1st floor firestopping complete.
- 1st floor taping and sanding complete.
- Elevator installation started.
- On site sidewalks complete.
- Landscaping complete.
- Poly and Sand under modulars complete.
As at September 25, 2009
- M&E Rough in complete.
- Exterior Windows complete
- Firestopping complete -Cladding ongoing.
- Interior board complete.
- Tape & Sand 2nd floor complete.
- Prime & 1st coat 2nd floor complete.
- 2nd floor Millwork started.
- 2nd floor Flooring started.
- Tape & Sand 1st floor started.
- Prime & 1st coat main floor started.
- T-Bar 2nd floor complete.
- Landscaping started.
As at August 25, 2009
- Masonry Veneer complete.
- Mechanical and Electrical exterior wall rough ins complete.
- Roofing complete.
- Cladding ongoing.
- Interior stud complete.
- Interior Masonry complete.
- Aluminum windows ongoing.
- Site curbs complete.
- Screw pile weld plates complete.
- Parking lot lighting/plugs complete.
- Interior board ongoing.
- Taping and sanding started
- Asphalt Paving complete
- Electrical Distribution started.
As at July 25, 2009
- Masonry Veneer ongoing.
- Mechanical and Electrical exterior wall rough ins complete.
- Roofing ongoing.
- Cladding ongoing.
- Interior stud complete.
- Interior Masonry ongoing.
- Aluminum windows ongoing.
- Site curbs complete.
- Screw piles complete.
- Parking lot lighting/plugs ongoing.
- Interior board started.
- Taping and sanding started
- Asphalt Paving started.
As at June 25, 2009
- Masonry Veneer on going.
- Mechanical and Electrical exterior wall rough ins complete.
- Roofing on going.
- Cladding started.
- Interior stud complete.
- Interior Masonry ongoing.
- Aluminum windows ongoing.
- Site curbs started.
- Screw piles complete.
- Parking lot lighting/plugs started.
As at May 25, 2009
- Interior Masonry on 2 floor complete.
- Mechanical and Electrical under slab complete.
- Mechanical and Electrical exterior wall rough ins on going.
- Roofing started.
- Site Services complete.
- 2nd floor slab complete.
- Masonry Veneer started.
- Cladding vapour barrier started.
- Main floor slabs complete.
- Roof Anchors Complete.
- Interior stud on going.
As at April 25, 2009
- Exterior Stud and Board complete.
- Interior Masonry started.
- Parapets and Roof Curbs complete.
- Mechanical and Electrical under slab started.
- Mechanical and Electrical exterior wall rough ins on going.
- Roofing started.
- Site Services Started.
- 2nd floor slab compete.
As at March 25, 2009
Construction: Over the last month the south masonry fire wall and the exterior block walls in the gym have been completed. Structural steel erection has been completed. Metal deck on the roof and second floor have been completed. Exterior steel stud and board, mechanical and electrical rough ins of the second floor have commenced and are on going.
Design: “Issued for Construction” drawings have been completed and issued to all sites for use. Some changes are being made through RFI’s and Site Instructions.
As at: February 25, 2009
Construction: Over the last month the north masonry fire wall has been completed. Structural steel erection has been completed with the exception of plumbing and torqueing of the roof.
Design: Issue for construction drawings and specifications have been issued with site instructions being issued to deal with any concerns. Issue for contract drawings and specification will be released shortly.
As at: January 25, 2009
Construction: Since the last report the elevator walls are complete to the under side of the roof. The deep underground has now been completed. Grading for the modulars is also complete.
Design: The design has advanced over the past month with the completion of many specific details and the specifications.
As at: December 25, 2008
Construction: Excavation and backfilling for the pile caps and grade beams has been completed. Formwork for the pile caps and grade beams is complete. Elevator walls are poured to the second floor level.
Design: Drawings have prgressed to 95% complete and issued for construction review drawings have been posted.
As at: November 25, 2008
Construction: Piling is now completed (excluding screw piles). Excavation for grade beams is now complete. Formwork for grade beams is on going with 50% of them being completed. Elevator pit slab has been poured with the walls beginning early next week.. Excavation for the pile caps has started and form work will begin by the end of the week. Over the next month it is anticipated that the grade beams will be 100% complete along with the pile caps. All of the backfilling will be complete and ready for steel. Expected delivery date of steel on site is January 12, 2008.
Design: Since the last report period, design has advanced and is now 92% complete. Over the next month we anticipate having the design complete to I.F.C. drawings.
|